Construction
and Renovation Archive
|
| |
|
|
|
|
6/05/02
- Renovation Plans for both the Main House and Back House are
finalized. Construction will begin after two underground oil
tanks located on the property are removed and as long as no
soil contamination is found.
|
|
|
| |
|
|
|
|
6/7/02
- Two underground oil tanks were removed, one located beside the
main house along Pickard Lane, the other located next to the Back
House. Soil surrounding the tanks was sent to be tested for contamination
and will be reviewed immediately. Results from the tests will
be available on June 11, 2002.
|
|
|
| |
|
|
|
|
7/23/02
- The loan closing occurred today and
construction plans are being finalized.
6/11/02
- The tests for soil contamination after the removal of the oil
tanks came back negative. Information will be posted soon on the
date for the beginning of Construction. Check back soon!
|
|
|
| |
|
|
|
|
9/23/02
- Currently
the both houses are being weather proofed and demolition to the
interior has begun. The interior demolition will take approximately
4 weeks to complete. After this has been completed, construction
on the exterior will begin. |
|
|
| |
|
|
|
|
10/04/02
- Demolition
is progressing on time. The kitchen, first and second floor bathrooms,
and the landing area on the second floor have been completely
removed from the main house. Work to remove the exterior siding
on both houses began this week, one week ahead of schedule.
|
|
|
|
%
|
|
|
|
|
11/19/02
- Rough framing
in both the main house and back annex has begun. Several areas of
structural damage were found in both houses. Those areas which were
identified have been resupported and will be replaced in the near
future. All exterior siding to both houses has been completely removed.
|
|
|
| |
|
|
|
|
12/28/02
- The new windows have arrived and are
currently being installed. The rough framing for both the main house
and back annex has been completed. The new staircase in the main
house has been built. Replacement siding on both houses is also
being installed and should be completed in the next three weeks.
Most of the work continues inside both houses, so poor weather conditions
have not slowed work. |
|
|
|
|
|
|
|
|
1/08/03
- Work continues to progress well.
The siding continues to be installed and most of the new windows
have been installed. The sub-flooring has been installed in space
where the old kitchen was, replacing the floor that had been damaged.
Work to replace the exterior framing to the back annex where terminte
damage was discovered is almost complete. The basketball court and
front fire escape have been removed to make room for the new parking
lot. |
|
|
|
|
|
|
|
|
1/17/03
-
The snow that fell overnight did not stop
work at the house. Electricians are busy installing the new wiring
in the main house and back annex. The grading for the new parking
lot has been completed and the trees behind the main house have
been removed, making room for the new parking lot in the back. New
siding is now on the front of the main house. Work will begin soon
on the footings for the addition to the main house for the new kitchen,
bathrooms, and bedrooms. |
|
|
|
|
|
|
|
|
2/5/03
- It has been a wet couple weeks.
Despite two days with snowfall and several days of rain, work has
contiued. Most of the new exterior siding on both the main house
and back annex has been installed. Only the exterior siding on the
back of the main house remains to be intalled, and that will be
done when the addition is completed. Most of the electrical wiring
has been completed in both houses. Work should begin in the next
few days on the plumbing, as well as the fire sprinkler installation. |
|
|
|
|
|
|
|
|
3/01/03
- Construction is projected to
be completed two months from today. Work on framing the new kitchen
and lower level bathroom has begun. Both the main and back house
have been primed and will be painted in the coming week, weather
permitting. Work continues on the plumbing and the new fire sprinkler
system has been roughed in. The new showers for the bathrooms
in the main and back house have been installed also. Dry wall
work should begin this week, as well as continued construction
on the new addition.
|
|
|
|
|
|
|
|
|
3/27/03
- Construction is on schedule to
be completed May 1. The exterior of both houses are being painted
with the final color. Inside both houses, dry wall work is close
to being finished. A new roof on both houses has been installed.
Work continues to complete the sprinkler system. The new addition
has been completed, and work inside continues. |
|
|
| |
|
|
|
|
4/17/03
-
Work on the main house has been
slowed due to poor weather conditions lately. However, progress
is being made. The dry wall has been installed in the old part of
the main house, and is currently being installed in the addition.
The dry wall work in the back house is close to completion. All
new windows have now been installed. In addition, work to connect
the gas line to the house begun. The concrete for the new side walks
and handicap ramp is in the process of being poured. |
|
|
|
|
|
|
|
|
5/6/03
- Construction is nearing an
end. Within the next week and a half all major work should be
completed. Right now, the interior of both the main house and
back annex are being painted. The tile floors for all the bathrooms
and the new kitchen have been laid. The new staircase in the main
house is being installed. The emergency fire staircase for the
back annex has been installed also. Work to install a new outdoor
stairwell for access to the basement in the main house has begun.
|
|
|
| |
|
|
|
|
5/19/03
- Renovations to the back annex
are nearing completion. Power has been restored to the back annx.
The main house is also close to being finished. All construction
equipment will be removed in the next day or so, and the hardwood
floors will be sanded and refinished. The new Kitchen equipment
will arrive soon and be installed. The parking lot will also be
paved soon. |
|
|
|
|
|
|
|
|
5/26/03
- All bathroom fixtures have been
installed in the back annex, as well as all light fixtures. All
that remains to be done with the back annex is for the floors to
be sanded and refinished. Work to the main house is in the final
stages. The carpet has been completely installed. The new light
fixtures have also been installed. Power should be restored to the
main house very soon. The new phone line is being installed and
the parking lot will be paved as soon as the wet weather subsides
for a couple days. The main house wood floors will be sanded and
refinished. The new kitchen equipment will be installed in the next
week. |
|
|
|
|
|
|
|
|
|
6/10/03
- The hardwood floors in the main
house have been sanded and refinished. Installation of the kitchen
cabinets is completed and all new kitchen equipment has been put
in place. If the warm, dry weather continues, the parking lot should
be paved by the end of the week. The new ice machine is also being
installed, as well as the new basketball hoop. A privacy fence will
be completed following the paving of the parking lot. Water is running
in both the main house and back annex. |
| |
|
|
|
|
6/20/03
- The rain over the past week has
slowed completion. However, most interior work is completed. Power
has been restored to the main house and the final steps to activate
the sprinkler system have begun. The back parking lot has been paved
and with some sun and a couple dry days the main parking lot should
be paved also. A new security light has been installed in the main
parking lot. The front sidewalk will be completely replaced with
new brick. The front porch will be sanded and repainted in the coming
week. |
|
|
|
|
|
|
|
|
|
|
7/02/03
- The main parking lot has been
paved and a security light has been installed. A privacy fence
has been installed on the Pickard Lane side of the house. A new
brick walk has also been installed in the front yard. With the
construction now completed, the application process for the proper
permits has begun. As soon as the final occupancy permit is granted,
the house will be turned back over to the Gamma Nu Foundation,
Inc.
|
|
|
| |
|
|
|
|
7/10/03
- The front porch to the main house
has been sanded and repainted, as has the staircase in the back
annex. A new drain system was installed for the back annex to help
prevent water from collecting underneath the building. The landscaper
is in the process of landscaping the front yard and areas around
the parking lot. |
|
|
| |
|
|
|
|
7/25/03
- The landscaping has been completed.
Final painting to both the interior and exterior of both houses
will occur this week. Stainless steel counter tops have been installed
in the kitchen for durability. All bedroom furniture has been delivered
and assembled. Final
inspections are occurring to secure the proper permits. |
|
|